$NBIS running late in Vineland ($MSFT contract)...
Before I give you my breakdown of this topic, let me make one thing clear. This isn’t me taking a victory lap on behalf of $IREN investors.
$IREN is down 59% YTD, while $NBIS is still up 24%.
That said, I’m a fundamentally driven investor with a long-term perspective, which is the angle I’ll be taking here.
I’ve long preferred $IREN over $NBIS, and still do, largely because of the companies’ very different approaches to expansion.
$IREN took a bottom-up approach, locking in secure, grid-connected power years in advance while you still could, and subsequently building 100% of its data center footprint in-house.
$NBIS, in contrast, has relied heavily on leasing data center capacity, also called colocation, from third-party developers, which in large part explains why it was able to scale this quickly over the past ~24 months.
The problem with a colocation-heavy approach is that it’s inherently less reliable, since much of the development process sits in the hands of third parties.
$NBIS is now learning that the hard way, with its colocated Vineland site, used for its $17.4B $MSFT contract, running into severe delays.
In fact, the delay is so significant that the full deployment has been pushed back from a year-end deadline toward Q2 of next year. In other words, up to half a year.
Management now expects just over half of the $MSFT capacity to be delivered by year-end, causing full-year revenue guidance to slip from $3.2B to $3.1B at the midpoint, while the $7–9B year-end ARR target has been reduced to ">$7B" and pushed to February.
Ironically, $IREN's own >$4B year-end ARR target has also just been pushed toward January / February amid a delay in its contracted $MSFT capacity.
On the surface, these two situations look remarkably similar, yet they could hardly be more different.
$IREN's delay was caused by a request from none other than $MSFT itself to make a networking design change mid-buildout, just months before delivery, with supplier timing adding to it.
And with $IREN being “here to say yes to customers, not no,” as Co-CEO @danroberts0101 put it, they obliged and absorbed a 1-2 month delay.
$NBIS's delay, on the other hand, is being caused by the third-party developer behind Vineland, DataOne, which is now responsible for a slip of 2 quarters.
$NBIS CEO Arkady Volozh said so himself:
“This is one of the sites which we build not ourselves directly, but with the help of third-party constructors. As you can expect, many more things may go wrong in such sites.”
More specifically, this delay was caused by the inability to secure power generation in time.
Vineland is a behind-the-meter (BTM) project, meaning the power is not grid-connected but instead relies on on-site generation.
The problem with that approach, as I have repeatedly explained over the past couple of years, is that generating hundreds of MW of power from gas comes with a massive amount of baggage and strings attached.
DataOne found this out last December, when the NJ state issued a notice of deficiency on its application to run 32 “Bergen” gas engines around the clock to power the site.
In plain English, the permits weren’t coming any time soon...
The state followed up in January by questioning whether the site should be permitted together with a neighbouring business, which could have meant far stricter rules, and by March DataOne was telling regulators it was exploring alternatives.
Also notice that DataOne only filed that application three months (extremely late) after $NBIS signed its $MSFT contract, which shows how vulnerable you become when you rely on third parties.
The site’s main problem to begin with is that it sits right next to homes and farmland, which makes local approvals far harder to come by.
DataOne and $NBIS then shifted strategy in May by contracting Bloom Energy ($BE) fuel cells, a much “greener” but also costlier option, to save the project.
With no permits in hand and such a drastic change of strategy just a couple of quarters before the deadline, I knew Vineland wouldn’t be fully ramped by year-end.
I called that out at the time, and took a lot of pushback from $NBIS bulls for it.
I wasn’t alone in that either, as @FransBakker9812, @jiahanjimliu and @ilzmcfly followed the Vineland story closely throughout the year and did excellent coverage on it, flagging the warning signs as they came up.
Management’s official reason is that DataOne unexpectedly shut off its gas engines amid the transition to Bloom Energy fuel cells.
However, anyone with a brain could have seen that coming...
DataOne had been running those engines without air permits since late 2025, and by the summer the state was closing in.
In late August, DataOne told regulators it would start phasing out engines, and in September the NJ DEP fined it $1.07M and gave it 45 days to apply for permits. DataOne is still contesting both.
I find it a bit ridiculous that $NBIS management insisted for months after the $BE announcement that Vineland was still on track for year-end delivery. In effect, they were counting on DataOne running unpermitted gas engines until the Bloom capacity was fully installed.
Either that, or they were ignorant of the fact that DataOne had no permits, which would arguably be an even worse look given that this information was publicly available.
Whatever the reason, this is a bad look. No other way to cut it.
In aggregate, this entire fiasco sums up the $IREN thesis.
Developing your own sites, being your own landlord, and having a >5 GW pipeline of secured grid power, alongside >35 GW of additional early-stage pipeline, means you don’t have to rely on sketchy third-party developers that don’t even have secured power.
Now, to be fair, $NBIS is fully aware of this and is actively moving away from the colocation-heavy model, having started construction on multiple self-owned data center projects.
For anyone interested in learning more about that, I recently covered its site portfolio, along with the potential strings attached to the individual projects, in a dedicated $NBIS deep dive for subscribers.
In any case, given that $IREN has severely underperformed $NBIS this year, this isn’t a “gotcha moment.” Anyone who held $NBIS from the beginning of the year has done better, so congrats on that.
But I believe now is as good a time as any to take another look at $IREN if you haven’t already.
There is a lot to look forward to in 2027, which I’m very excited about.
Thank you for reading, cheers!